LONDON UNDERGROUND
 

Description of Works:

Installation of concrete units on the bottom of the Thames and provision of protection to the underground tunnels with combi - walls and sunken concrete prefab roof sections. Dredging works.

 

The project was split into three sections

   
 

- Construction of Pre Cast Units. More details
- Strengthening of the Bakerloo Underground Tunnels. More Details
- Strengthening of the Northern Line Underground Tunnels. More Details

   
Client: London Underground Limited
Invoiced Sum: € 22.129.538
Tender Value: € 15.620.850
Start of Works: 01 March 1996
Completion Date: 01 September 1997
Herbosch - Kiere Share Of Joint Venture:
50 %